| |
|
|
 |
|
Project One:
House Build at Peraliya
Location:
North of Hikaduwa on the Galle Road
Impact of
the Tsunami: Massive destruction, 3,000 villagers
killed, including 1,640 people who climbed on a
nine-carriage train for safety. It was derailed less than
100 metres from where the house stood and is officially the
world's worst ever train disaster. The tsunami went several
kilometres in land, and destroyed 90% of the village.
|

|
|

|
Project
Details: Rebuild a three bedroom bungalow situated less
than 100 metres behind the sight of the train derailment.
Only one wall and parts of the footings remained sound, so
it was a massive undertaking.
The job
required removing unsafe walls, taking up the damaged floor,
clearing the site, removing rubble, securing and replacing
the damaged footings, building external and internal walls,
building the roof, rendering the walls, plumbing the kitchen
and bathroom and wiring the house. Dubbed 'Mission
Impossible' by the team!
Timescale - 9
days!
|
|

|
|
Weather
Details: Average temperature 35 degrees, but it topped
40 on several days. Heavy rain in late afternoon.
Workforce:
Along with four local masons, and a few 'ad hoc' labourers
almost every member of the team helped in some way.
Problems and
Issues: To begin with, securing a JCB, a cement mixer
and a contractor with sufficient labour was a problem.
However, once this was done, Aramitar and his team sourced
the materials and provided the expertise to make sure the
job got done.
The heat was
also a major problem as it regularly topped 40 degrees.
Avoiding sunburn and dehydration was difficult, but we soon
learnt to respect Sri Lankan working methods (avoiding the
hottest part of the day, keeping heads covered to keep cool,
and not over exerting ourselves). |

|
|
 |
|
 |
Other
Information: The original house was built in the 1970's
by Mr Armarasena for his wife (see picture below), and their
son and daughter. Only the son was at home when the tsunami
struck, and he had to climb on the roof with his cat and dog
to escape. He saw the second wave approaching, carrying
buildings and people in its wake. He was stuck on the roof
for several hours. Just at the edge of the building site (30
feet from the front dor) are two mass graves where the
bodies of over 1000 of those who died on the train were
buried. Several bodies were later found in the trees, and
the bodies of two babies were also discovered in the family
well, all of which the family themselves cremated according
to Buddhist rite. Bones are still being uncovered in the
undergrowth. |
|
Building
Details:
After removing
the rubble, loose walls, and clearing out the flooring, we
used a JCB to reveal the footings, which needed considerable
work to make them secure. Once the space between the
footings was backfilled with rubble and then compressed
down, the walls were built on top of the footings, the
floors levelled and the roof constructed with local wood.
Finally, the walls were rendered. The tiles were laid on the
roof the day after we flew home. We tried, where possible,
to re-use bricks which were salvageable. |

|
|


|
|
UPDATE -
12/04/2006
The house has now been
finished, handed over and is now being lived in. Pictures of
the completed house to follow ASAP.
Click here for next project |
|
|
|
|

|